Construction Progress

  • 2027/08/27 Complete all construction for Bethel Hall
  • 2027/08/10 Complete interior installations and finishes
  • 2027/05/10 Finish courtyard construction
  • 2026/12/26 Finish building shell
  • 2026/09/01 Finish new foundation work
  • 2026/06/20 Begin site demolition
  • 2026/05/27 Building permit approved
  • 2025/10/28 Construction drawings completed, submitted permit application to city
  • 2025/10/18 Current site cleared and moved
  • 2025/09/12 Construction drawings 70% complete, awaiting geotechnical report to complete foundation design
  • 2025/08/07 Contractor 2nd construction cost estimate completed, exceeding initial budget by 22%
  • 2025/07/07 Construction drawing phase begins
  • 2025/06/15 Father's Day special offering
  • 2025/06/10 City completed design project review approval (Although design review passed, fire department, public works, and building construction departments required additional materials, causing a 3-month delay)
  • 2025/05/15 Design development phase completed
  • 2025/05/11 Mother's Day dinner fundraiser
  • 2025/02/03 City preliminary review completed and requested additional materials
  • 2025/01/20 Design development phase begins
  • 2024/10/07 Confirmed with architect and builder to reduce construction costs to meet church budget
  • 2024/09/09 Design schematic phase completed, submitted to city for review
  • 2024/06/11 Design schematic initial draft completed
  • 2024/03/07 City approved demolition and reconstruction
  • 2023/06/30 Selected project team
  • 2023/03/26 Established building committee

* Red indicates estimated future progress

Currently Bethel Hall construction permit is in the second round of review and approval process. Due to seemingly ever-increasing requirements in construction standards, we have to add in certain details in our construction documents which were considered optional previously. As a result, the projected construction permit approval has been pushed to the end of May. In the meantime, our church project management (PM) team has started meeting with our architect and construction contractor on every Tuesday, to facilitate communication and ensure work progress. And our PM team has completed our construction contractor’s construction insurance review; PM team also received bids for the design of the safety and security system and proposals for material and color themes for interior/exterior design, and established a workgroup to help review and collect feedback on these bids/proposals.