- 2027/09/27 Complete all construction for Bethel Hall
- 2027/09/10 Complete interior installations and finishes
- 2027/05/10 Finish courtyard construction
- 2027/01/26 Finish building shell
- 2026/09/01 Finish new foundation work
- 2026/07/01 Begin site demolition
- 2026/06/18 Building Permit officially approved
- 2026/06/05 Building permit passed review
- 2026/05/15 State Water Board issued non-case letter concerning soil and soil gas safety
- 2025/11/02 Construction drawings completed, submitted permit application to city
- 2025/10/18 Current site cleared and moved
- 2025/09/12 Construction drawings 70% complete, awaiting geotechnical report to complete foundation design
- 2025/08/07 Contractor 2nd construction cost estimate completed, exceeding initial budget by 22%
- 2025/07/07 Construction drawing phase begins
- 2025/06/15 Father's Day special offering
- 2025/06/10 City completed design project review approval (Although design review passed, fire department, public works, and building construction departments required additional materials, causing a 3-month delay)
- 2025/05/15 Design development phase completed
- 2025/05/11 Mother's Day dinner fundraiser
- 2025/02/03 City preliminary review completed and requested additional materials
- 2025/01/20 Design development phase begins
- 2024/10/07 Confirmed with architect and builder to reduce construction costs to meet church budget
- 2024/09/09 Design schematic phase completed, submitted to city for review
- 2024/06/11 Design schematic initial draft completed
- 2024/03/07 City approved demolition and reconstruction
- 2023/06/30 Selected project team
- 2023/03/26 Established building committee
* Red indicates estimated future progress
The City has approved our building permit, preliminary construction work has begun and expected to complete in two weeks, which includes installation of construction fences, removal of some pipes and wires, and installation of temporary isolation walls. Demolition of existing building will begin on Jul 1, 2026.